Glenlee – 132KV Civils & Balance of Plant
The works at Glenlee form part of the Kendoon to Glenlee Reinforcement, which includes the extension of the 132kV network in south west Scotland.
The RIIO‐T1 shunt reactor modernisation programme has identified the need to replace the
existing oil filled shunt reactors (R1 & R2) at Smeaton 400/275/132kV substation. The new
Shunt Reactors will have nominal capacity rating of 60MVAr.
Click image to enlarge
The Scope of Works will include the following activities:
‐ Substation Primary Works:
2 off 145kV Dead Tank Outdoor Circuit Breakers
15 off 33kV Surge Arrestors
2 off 33kV NER
58 off 36kV Post Insulators
2 off Earthing Auxiliary Transformer
4 off Gevea 33kV Disconnector + Earth Switch
2 off Sadtem 36kV outdoor oil Voltage Transformer
3 off Post Current Transformer
3 off Slip‐Over Current Transformer
‐ Supply & installation of galvanised support Steel Structures for installation of all switchgear, main plant & ancillary equipment.
‐ 33kV cable works
‐ Supply, Delivery, handling, installation, terminating & commissioning of all low voltage AC & DC cables, multicore cables & multi‐pair cables.
‐ Supply, installation and testing of all the above ground earthing.
‐ Supply, handling, installation, testing and commissioning of all busbars, clamps & connectors including flexible connections and stranded conductors.
‐ Supply, delivery, installation, testing and commissioning of all mechanical interlocking associated with the 33kV switchgear and associated plant and equipment.
‐ Supply, installation, earthing, testing and commissioning of the substation compound floodlighting.
‐ Supply, delivery, handling, installation, testing and commissioning of Bay Marshalling Kiosk and Supplies Pillar.
‐ Supply, delivery, handling, installation, testing and commissioning of 33kV VT Fuses associated with each Shunt Reactor.
‐ Supply and installation of Labels and Nameplates
‐ Upgrading works of the existing standby diesel generator by installing a new fuel tank to allow 168 hour operation under full load conditions.
‐ Supply and installing 2 off non‐conductive height restriction barriers upon entry into the 33kV reactor compound.
‐ Supply, installation and fitting out of the battery system enclosure located adjacent to the existing building.
‐ Producing all wiring diagrams, termination diagrams, mark‐ups and all other documentation necessary to complete the installation and commissioning of the equipment.
‐ Installation, testing and commissioning of new front sheet for R1 panel on an existing unused frame.
‐ Installation, testing and commissioning of new free issued stand‐alone R2 protection and control panel.
‐ Installation, testing and commissioning of loose P&C relays and equipment for SGT2 Transformer Protection Panel.
‐ Installation, testing and commissioning of loose P&C relays and equipment for SGT1 Transformer Protection Panel.
‐ Installation of a new free‐issued 110V DC system.