Smeaton – Shunt Reactors Modernisation BoP

The RIIO‐T1 shunt reactor modernisation programme has identified the need to replace the
existing oil filled shunt reactors (R1 & R2) at Smeaton 400/275/132kV substation. The new
Shunt Reactors will have nominal capacity rating of 60MVAr.

 

The Scope of Works will include the following activities:
‐ Substation Primary Works:
2 off 145kV Dead Tank Outdoor Circuit Breakers
15 off 33kV Surge Arrestors
2 off 33kV NER
58 off 36kV Post Insulators
2 off Earthing Auxiliary Transformer
4 off Gevea 33kV Disconnector + Earth Switch
2 off Sadtem 36kV outdoor oil Voltage Transformer
3 off Post Current Transformer
3 off Slip‐Over Current Transformer

‐ Supply & installation of galvanised support Steel Structures for installation of all switchgear, main plant & ancillary equipment.
‐ 33kV cable works
‐ Supply, Delivery, handling, installation, terminating & commissioning of all low voltage AC & DC cables, multicore cables & multi‐pair cables.
‐ Supply, installation and testing of all the above ground earthing.
‐ Supply, handling, installation, testing and commissioning of all busbars, clamps & connectors including flexible connections and stranded conductors.
‐ Supply, delivery, installation, testing and commissioning of all mechanical interlocking associated with the 33kV switchgear and associated plant and equipment.
‐ Supply, installation, earthing, testing and commissioning of the substation compound floodlighting.
‐ Supply, delivery, handling, installation, testing and commissioning of Bay Marshalling Kiosk and Supplies Pillar.
‐ Supply, delivery, handling, installation, testing and commissioning of 33kV VT Fuses associated with each Shunt Reactor.
‐ Supply and installation of Labels and Nameplates
‐ Upgrading works of the existing standby diesel generator by installing a new fuel tank to allow 168 hour operation under full load conditions.
‐ Supply and installing 2 off non‐conductive height restriction barriers upon entry into the 33kV reactor compound.
‐ Supply, installation and fitting out of the battery system enclosure located adjacent to the existing building.
‐ Producing all wiring diagrams, termination diagrams, mark‐ups and all other documentation necessary to complete the installation and commissioning of the equipment.
‐ Installation, testing and commissioning of new front sheet for R1 panel on an existing unused frame.
‐ Installation, testing and commissioning of new free issued stand‐alone R2 protection and control panel.
‐ Installation, testing and commissioning of loose P&C relays and equipment for SGT2 Transformer Protection Panel.
‐ Installation, testing and commissioning of loose P&C relays and equipment for SGT1 Transformer Protection Panel.
‐ Installation of a new free‐issued 110V DC system.