Llynfi Afan Wind Farm – Delivered

Llynfi Afan Wind Farm – Delivered

posted in: News | 0

NRS Group recently delivered the complete Balance of Plant Contract for the 12 turbine (Gamesa G80) Llynfi Afan Wind Farm project. All works were managed and delivered in-house, with NRS Group HV Power Solutions delivering the Electrical Balance of Plant Works, Commissioning and Energisation the Wind Farm upon completion.

This ability to deliver the complete turnkey package without sub-contracting the EBoP works was a significant factor in the successful delivery of this project on an incredibly challenging programme, with less than 10 months between works commencement and WF Commissioning.

Key works elements included the construction of 12 no. turbine foundation and hardstandings, the 8.5KM site infrastructure road network, all building, civils and Electrical Balance of Plant works associated with the 33kV Wind Farm Substation and turbine connections and the installation and connection of over 40 km of cable, including energisation and provision of SAP services.

The wind farm, situated in South Wales near Abergwnfi in Neath Port Talbot, will produce 24MW`s of power, serving the equivalent of 14,370 homes